The Allahabad High Court has offered a reprieve to Sunshine Trade Tower Pvt Ltd, a developer grappling with the Noida Authority’s failure to construct promised approach roads for its commercial plot. In a landmark decision, the court granted a ‘zero period’ waiver, providing significant relief to the embattled developer.
The protracted legal battle spanning a decade has its roots in the Noida Authority’s consistent delay in fulfilling its obligation to build the necessary roads. These infrastructural shortcomings had led to the accumulation of dues for the developer, culminating in a threat of lease deed cancellation.
The court, however, recognized the developer’s plight and intervened to prevent an unjust outcome. The ruling emphasizes that this decision is specific to the case and should not be interpreted as a general precedent for similar situations.
To ensure a fair resolution, the court has directed the Noida Authority CEO to make a decision on the developer’s representation based on its ‘zero period’ policy within a stipulated timeframe of three months. This development underscores the challenges faced by developers when confronted with infrastructure delays and highlights the critical importance of timely execution of civic amenities.
The case serves as a stark reminder of the potential consequences for developers when government agencies fail to meet their commitments. It also underscores the need for robust legal recourse for developers facing such hurdles.